Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because---
(E)the new managers have no need to justify the earlier decision to maintain the project.
能帮我分析一下这道题吗?conclusion 和evidence各是什么?答案为何是E? |
|