Which of the following best completes the passage below?
When a project is failing and should be terminated, plan to bring in a new manager. New managers are more likely to terminate the project than are the original managers because---
(E)the new managers have no need to justify the earlier decision to maintain the project.
能帮我分析一下这道题吗?conclusion 和evidence各是什么?答案为何是E?
作者: linsonstudy    时间: 2003-12-1 22:53

project是原来经理的主张,原来的经理会顾及面子,力图保留原来的project,如果它成功了就可以挽回自己的脸面。而project并不是由新的经理提出的,而且本来就不太好,所以新的经理更倾向于终止它。